Chile’s Codelco is investigating new evidence of over-reported copper production in 2024 and 2025, the state-run miner said on Tuesday, a probe that could further stoke industry concerns about the reliability of the firm’s production figures as it struggles to lift output.
The reported figures showed artificially inflated output from the Ministro Hales and Salvador divisions during those years, potentially due to both mines claiming the same production, it added.
The finding was revealed amid a production audit for 2024 and 2025 ordered this year by Bernardo Fontaine, the newly appointed chairman, as the miner faced scrutiny over its debt and long-standing production challenges.
Codelco previously fired an executive and took disciplinary action against others following an audit into improper reporting of its 2025 production involving the Chuquicamata and Ministro Hales mines.
In those cases, materials that required further processing should not have been reported as finished products, it said.
Codelco is now investigating how the newly detected inconsistencies could have occurred, and whether there will be financial impacts.
“Based on the information available so far, the inconsistency seems to be that the same material was recorded as production by more than one division,” Codelco said in a statement.
The firm tapped consulting company EY to conduct an external audit and submitted the new findings to the public prosecutor’s office.
“Management has decided to thoroughly investigate any irregularity, determine who is responsible, apply the appropriate sanctions, and seek to recover any financial losses that may have occurred,” CEO Jorge Gomez said in a statement.
Codelco, one of the world’s largest copper producers, aims to produce 1.7 million metric tons of copper a year by 2030, but its leadership has said output in coming years is likely to stay similar to current levels. Last year’s production at Codelco’s own mines stood at 1.33 million tons.
The miner is working to recover from a slump in 2022 and 2023 when production fell to two-decade lows.
In March, Reuters reported that leading copper industry analysts and former Codelco executives questioned its reported surge in output at the end of last year, figures that helped the company meet its annual production target.
(Reporting by Fabian Cambero; Writing by Paolo Laudani; Editing by Daina Beth Solomon and David Gregorio)